Fabrication
and construction of the Euro-MARS took place in mid-2002 in Denver,
Colorado, USA. The actual fabrication of parts for the habitat is
being undertaken by the Rio Grande Company, with physical construction
work being carried out on their back lot. All construction activities
are being overseen by Frank Schubert, the MARS Programme Project
Manager, aided by Matt Smola and Dewey Anderson.
The construction
work was completed in a number of stages
March saw the
various components of the hab fabricated by the Rio Grande Company,
with initial construction (test-fitting the compnents) taking place
at the end of April, prior to the hab being properly put together
through May of 2002.
As Euro-MARS
comprises three decks, rather than two (as with the F-MARS and MDRS
units), the design and construction of the hab is substantially
different to the earlier MARS units, which carry the majority of
their weight through the wall panels themselves. However, Euro-MARS
carries its mass through the framwork of the lower and mid-decks,
even transferring the load to the six "landing legs".This
results in a far more even distribution of mass for the Euro-MARS,
and enables it to withstand very high wind forces - a vital requirement,
given northern Iceland can be whipped by the full fury of North
Atlantic storms. .
Once assembled
on-site, Euro-MARS was dismantled and loaded on to trucks for shipment
to Chicago, where it was placed on display at the Adler Planetarium.
A complete gallery
of construction images is also available
on this web site. |

Lower Deck and Leg
Struts
April 21st 2002

Lower Deck
Flooring
April
25th 2002

Test-fitting
Wall panel Frames
May 9th, 2002

Skinned
Wall Panels in Place
May 15th 2002
|